Present value and NPV in 10 minutes

Why future money is worth less today, discount factors, and when to accept a project.

Present value

Money now can earn a return, so money later is worth less today. Present value = future amount ÷ (1 + r)^t, where r is the yearly rate as a decimal and t is years.

Passages often give discount factors in a table (for example 0.926 for one year at 8%). Multiply each cash flow by its factor instead of dividing by powers.

Net present value

NPV adds up the present values of all cash flows, with the initial cost counted as negative. Positive NPV: the project earns more than the discount rate, so accept it. A higher discount rate lowers NPV.

The payback period ignores timing and anything after payback, so it can disagree with NPV.

Check yourself

  1. Cost €1,000 today, €1,100 in one year, rate 10%. NPV?

    Show answer

    Zero: 1,100 / 1.1 = 1,000, which exactly repays the cost.

  2. Does raising the discount rate raise or lower NPV for a normal project?

    Show answer

    Lower it: future cash flows are divided by a bigger number.